SUDBURY, October 13, 2020 – After more than 100 years of operation, the iconic headframes and other buildings at Vale’s Stobie Mine site will be demolished over the next few months. The demolition follows Stobie Mine operations being placed on care and maintenance in 2017.
“The aging headframes are being demolished to reduce maintenance costs and pave the way for potential new development currently being studied at the Stobie Mine site,” said Patrick Boitumelo, Head of Mining & Milling for Vale’s North Atlantic Operations.
This work will be completed between mid-October and mid-December, with all three headframes at Stobie Mine demolished. Shafts Seven and Eight will be dismantled by carefully removing pieces of the headframes from the top down starting October 13th. The Nine Shaft will be safely blasted down the week of November 9th. Some buildings at the site such as the crusher plant, mill and hoist building have already been removed with a few more also scheduled for demolition.