Inmet to battle $5.1-billion hostile takeover bid – by Pav Jordan (Globe and Mail – January 16, 2013)

The Globe and Mail is Canada’s national newspaper with the second largest broadsheet circulation in the country. It has enormous influence on Canada’s political and business elite.

Inmet Mining Corp. has a week to respond officially to a hostile takeover bid from rival First Quantum Minerals Ltd., but few expect anything short of a rejection of the $5.1-billion offer.

The owner of the coveted Cobre Panama copper project in Central America has until Jan. 24 to respond, and people familiar with the situation say it will come out swinging, recommending against the takeover and signalling progress in its search for an alternative palatable to shareholders.

Central to its defence will be a critical analysis of First Quantum’s track record on cost controls, meeting production targets and building mines in Latin America, said a source.

The company will allege First Quantum has a history of underestimating capital costs, as well as argue the Vancouver-based firm has no experience with capital projects the size of Cobre Panama, which will cost $6.2-billion to put into production.

How this plays out could prove critical to Inmet’s defence because the First Quantum bid of $72 a share is in cash and stock, which means the hostile suitor must convince investors of the value of its own shares.

“The board is expected to recommend against the offer,” said a source familiar with the Inmet stance. The source said Inmet will also follow the playbook of takeover defence tactics and point to confidentiality agreements and standstills it has signed with unnamed parties who might become rival bidders.

Agreements could also be signalled with parties interested in taking a minority stake in Cobre Panama, which would make a takeover by First Quantum far less likely.

Executives of Africa-focused First Quantum, known in the industry for its proven engineering team, believe they can build Cobre Panama more efficiently than Inmet. As proof, they point to the Sentinel project they are building in Zambia that will have similar output but will be completed at about a third of the price, some $2-billion.

They also point at projected capital costs at Cobre Panama that have gone from $3.5-billion in 2008 to $4.3-billion in 2010 and $6.2-billion today.

Cobre Panama will be the biggest mining project in the history of Central America, as well as the largest capital project in Panama since the Panama Canal and its subsequent expansion.

For the rest of this article, please go to the Globe and Mail website: http://www.theglobeandmail.com/report-on-business/inmet-to-battle-51-billion-hostile-takeover-bid/article7377773/