Vale’s $2-billion environmental project in Copper Cliff remains a go, but its completion date is being extended into 2016, the company said Friday.
“To mitigate risks associated with the (Clean Atmospheric Emissions Reduction) project, we now intend to take some additional time to complete the project, both to better position ourselves for success and to address short-term cash-flow constraints in light of current market conditions,” Vale spokeswoman Angie Robson said Friday.
“The end result of this approach is a change in schedule for some of the gas capture components of the project to align with our scheduled planned maintenance period in September, 2015.
“The (planned maintenance period) is the available window to complete the final tie-in work, so that all of the new systems will be ready for start-up and commissioning once the September 2015 (planned maintenance period) ends. The end result will mean the project will be completed in 2016 instead of the end of 2015.”
The massive project will modernize Vale’s Copper Cliff smelting complex and result in a significant reduction in sulphur-dioxide emissions.