Xstrata Nickel Announces Restructuring of Sudbury Operations (Company Press Release)

Toronto, 9 February 2009

Xstrata Nickel today announces plans to restructure its Sudbury operations in response to ongoing challenging market conditions.  The restructuring follows the announcement in November 2008 of the accelerated closure of the end-of-life Craig and Thayer-Lindsley operations at Sudbury, both of which will cease operations with immediate effect.

As a result of the restructuring, the Fraser Mine Complex will be placed on care and maintenance and associated support and administrative functions will be reorganized. The Strathcona Mill, with annual capacity of 2.7 million tonnes of ore, will be reduced to two work shifts from four as a result of reduced feed. In addition, the Fraser Morgan development project will be deferred. This project will be evaluated on an ongoing basis and may be re-initiated when economic conditions allow.

Today’s announcement does not impact the world-class Nickel Rim South project in the Sudbury basin.  The project remains on schedule to ramp up to 60% of its ultimate 1.25 million tonne per annum production capacity in 2009, equivalent to approximately 7,400 tonnes of nickel.  Nickel Rim South will become a low-cost, cornerstone operation in Sudbury, generating annual production of approximately 18,000 tonnes of recoverable nickel by early 2010. 

Read more

Xstrata Says Demand Collapsing, 686 Jobs Lost – by Bill Bradley

Northern Life, Greater Sudbury’s community newspaper, gave Republic of Mining.com permission to post Bill Bradley’s article. www.northernlife.ca

The global economic meltdown is now biting Greater Sudbury. Gone for good are 686 full-time jobs at Xstrata Nickel, after the company announced a major restructuring of its Sudbury operations.

“Demand for our product has collapsed,” said Marc Boissonneault, vice-president Xstrata Nickel, Sudbury on CBC Radio One, Monday morning.
“We can’t carry on business as usual.”

As a result, the following will occur:
– 686 permanent employee positions will be made redundant, affecting both union (600) and salaried (86) employees;
– three-day shutdown will take place immediately to implement restructuring and talk to employees;
– 300 employees will be moved to the higher-value Nickel Rim project, displacing some contractors;
– Fraser Mine will be placed on care and maintenance for now;
– accelerated closure of Craig and Thayer-Lindsley operations;
– Strathcona Mill will be reduced from four shifts to two;
– Fraser Morgan development project will be deferred to be evaluated and possibly re-initiated.